Overview
The Materials tab turns the measured work in your scope into a materials list (also called a bill of materials) — the goods you actually buy, in sheets, sticks, rolls and bags, with waste and pack sizes already applied. Every line points back to the sheet its quantity came from.
Where to find it: your project → Scope → Materials tab.
Step 1: Generate the materials list
Open your project and click Scope in the left navigation.
Click the Materials tab, to the right of Scope, Measurements and Base Measurements.
Click Generate Materials.
The Generating Your Materials List screen shows four stages: Reading Your Takeoff, Choosing Assemblies, Calculating Purchase Quantities and Checking the Numbers. When the last stage finishes, the list appears on the same tab.
Good to know: generation takes a few minutes. You can leave the page and come back to the Materials tab while it runs.
What's on the Materials tab
Materials are grouped by trade, for example Plumbing, HVAC and Electrical. Each line has these columns:
Material — the material, with a short description underneath.
Net qty — the quantity measured from your plans, before waste.
Waste — the waste percentage added on top. Defaults vary by type of material.
Purchase qty and Unit — what you buy. Quantities round up to whole units, and pack sizes show underneath, such as 100 LF per Roll or 6 LF per Stick.
Ordered qty and Purchase order — these show — on a newly generated list.
Reference — the sheet the quantity came from, such as A101.
Spec status — Derived, Specified or Assumed.
Example: 195 LF of supply piping with 10% waste is 214.5 LF, which rounds up to 3 rolls at 100 LF per roll.
Above the table:
Search materials — find a material by name.
Group by — Material or Scope item.
Status — All, Needs review or Confirmed.
Trade — All trades, or one trade that has materials.
Manage — Assumptions, Export and Clear materials.
Reviewing the assumptions behind your materials
When the plans don't state something, KonstructIQ uses a default and records it. Click Manage → Assumptions to see every default used, grouped by trade. Each one shows the default used (for example PEX for domestic water supply piping), what to verify, and the materials it affects.
Where a value can be set, such as Set per fixture or Avg run, type the real number into the field. Changing a default recomputes the materials it affects straight away — no re-analysis, no waiting. Click Back to Materials to return to the list.
Tip: start with lines marked Assumed in Spec status. These are the quantities that rest on a default instead of the drawings.
Adjusting a material line
Click a material to open its detail panel. It shows the material name, its spec, the scope item it came from, the sheet it was measured on, and the three quantities:
Net — the measured quantity.
Waste — the percentage, and whether it is the default for that type of material or an override on this line.
Purchase — the rounded quantity and its unit.
Type a new value in any of them to override it. An overridden line shows a note such as Typed over the derived net quantity and a reset icon (↺) that returns it to the calculated value.
You can also edit Net qty, Waste and Purchase qty directly in the table. Use Edit 1 Assumption in the panel to jump to the default that line relies on.
Exporting materials to Excel
Click Manage → Export. Checkboxes appear next to each material and trade.
Select individual materials, or tick a trade to select all of its materials. The counter shows how many are selected.
Click Export. Click Cancel to leave selection mode without exporting.
The export is an Excel spreadsheet (.xlsx). It is titled with your project name and Materials, shows the export date and how many materials it contains, and has the same columns as the table: Material, Net qty, Waste, Purchase qty, Unit, Ordered qty, Purchase order, Reference and Spec status. Waste is a plain number, so 10 means 10%.
Note: Export stays unavailable until at least one material is selected. Only the materials you select are in the file.
Clearing and regenerating the list
Click Manage → Clear materials to remove the list and start over. A confirmation shows how many material lines will be removed.
⚠️ Clearing removes your edits. Along with the material lines, it removes every waste factor and assumption you edited, catalog matches you confirmed on a line, resolved specs and the assumption ledger, and the verification audit if one has run. Your takeoff is not touched.
After clearing, the tab returns to Generate Materials. You can generate a new list at any time.
Troubleshooting & FAQs
I don't see a Generate Materials button. Open Scope → Materials. The button appears when the project has no materials list yet. If a list already exists, use Manage → Clear materials and then generate a new one.
Generation is taking a while. It takes a few minutes. You can leave the page and come back to the Materials tab.
Why is Purchase qty higher than Net qty? Waste is added to the net quantity, then the total rounds up to whole purchase units such as sticks, rolls or bags.
A quantity looks wrong. Click the line and check its Reference sheet. If a default is wrong, change it under Manage → Assumptions, or type over the value on the line. If the measurement itself is wrong, correct it with Edit Takeoff and generate the list again.
Will clearing materials change my takeoff? No. Clearing removes only the materials list and what was derived from it. Your takeoff stays as it was.
Will I lose my edits if I regenerate? Yes. Clearing removes your waste edits, assumption edits and confirmed catalog matches, so a regenerated list starts fresh.
Can I export only part of the list? Yes. Choose Manage → Export, then select just the materials or trades you want.
What file format is the export? Excel (.xlsx).
Quick Reference
Path: project → Scope → Materials → Generate Materials.
Check the defaults: Manage → Assumptions.
Export: Manage → Export → select materials → Export (downloads an Excel file).
Don't skip: the Assumed lines. They rest on defaults, not on your drawings.