Global Schedule: View and Compare Multiple Project Schedules

How to use the Global Schedule to view several projects' schedules at once: picking projects, the Calendar, Map, List, and Resource views, spotting overlaps and double-booked people, and how many schedules to load at a time.

Overview

The Global Schedule shows the schedules of more than one project on a single screen, so you can see how jobs overlap and where the same people are needed in two places. Each project gets its own color, and you choose which projects to show.

Where to find it: Projects → Schedules. Only projects that already have a schedule show items. To build a schedule for one project, see KonstructIQ Knowledge Base: Project Scheduling & To-Dos.


Step 1: Pick the projects to show

  1. From the top menu, click Projects, then choose Schedules. The page opens empty with the message Select projects to see their schedules.

  2. Click Project and tick the projects you want. Use the search box in the list to find a project by name.

  3. The schedules load. While they load you see Loading N schedules… next to Owner.

Each selected project appears in a color-coded legend under the toolbar, and its items use the same color everywhere on the page. Click the × in the Project filter to clear your selection.

Good to know: if you pick a project that has no schedule, a No schedules yet banner appears with a Create Schedule button. That project simply shows no items.


The four views

Use the tabs at the top of the page to switch views. Your selected projects stay the same.

  • Calendar — items on a calendar, shown as Week Agenda (the default), Day Agenda, Month, or Agenda. Use Today and the arrows to move through time. In Month, busy days collapse to a +N more link.

  • Map — numbered pins for each project on a map, with the selected week's items listed beside it. Use the Schedule and To Dos toggle to switch what the list shows. Projects without an address can't be placed and are counted in a note above the map.

  • List — items grouped by day, with Project, Start Date, End Date, Duration, Assignees, Status, and Progress columns.

  • Resource — one row per staff member or subcontractor, with the hours they are scheduled each day and the item they are on. Use the arrows to change weeks.


Finding overlaps and double-booked people

  1. Select two or three projects whose dates run at the same time.

  2. Open Calendar and switch to Month to see which weeks are crowded, using the project colors to tell the jobs apart.

  3. Open Resource to check people. If the same person or subcontractor shows hours on items from different projects on the same day, they are booked on both.

  4. Open List to see exactly which items start on the same day.

Tip: use the Owner filter to narrow the view, and Options to change the Row height to Small, Medium, or Large. Use the search box to find a project, client, or item by name.


How many schedules can I load at once?

There is no fixed limit and no warning message, but the more schedules you select — and the bigger each one is — the longer the page takes to load. A schedule built from a large estimate with dozens of line items is much heavier than a small one.

Best practice: compare two or three schedules at a time. Avoid loading several large, dense schedules together. If you need to review many jobs, work in groups, or use the List view.

As a rough guide from testing, a handful of schedules loaded in seconds and about a dozen loaded in under a minute, while a selection of more than twenty large schedules had not finished loading after more than a minute. These times depend on your data.


Troubleshooting & FAQs

  • The page is stuck on "Loading schedules…". You have probably selected too many schedules or a very large one. Clear the Project filter with the ×, then add projects back two or three at a time.

  • A project I selected shows nothing. It may not have a schedule yet. Open that project, go to Schedule, and click Create Schedule.

  • My project isn't on the map. The project needs a site address. Add it with Edit Project on the project's dashboard.

  • Can I see people who are working on two projects at once? Yes. Select both projects and open the Resource view. Each person's hours and items are shown by day.

  • Do I need a schedule on every project? No. Projects without a schedule just don't show items.


Quick Reference

Path: Projects → Schedules → Project → tick projects → choose Calendar, Map, List, or Resource.

Best practice: load two or three schedules at a time, and avoid loading several large ones together.

Don't skip: the Resource view when you are comparing jobs. It is the fastest way to catch a person booked on two projects.