Compare, Award, and Close Bids

How to track bid responses, add a bid you received outside KonstructIQ, review and compare bids with AI, award one to your estimate, reject bids, and edit or close a bid request.

Overview

Once a bid request is sent, KonstructIQ tracks every response in one place, helps you review and compare bids that rarely arrive in the same format, and folds the winning one into your estimate. This guide covers everything after sending — reviewing responses, adding a bid a sub emailed you directly, analyzing and comparing bids, awarding or rejecting, and what happens to the bids you don't award.

See Create and Send a Bid Request for building and sending the request itself.


Step 1: Track responses as they come in

Open the bid request and click the Responses tab to see every response, with the Subcontractor, the Source of the bid, the bid Amount, its Status, and the Date it came in. A bid you entered yourself shows its source as “Added by you,” so you can tell it apart from one a subcontractor submitted through the portal. A bid that's in shows Submitted; after you act on it, its status changes to Awarded or Rejected.

The lowest submitted amount is flagged Lowest. An eye icon next to a response means the subcontractor hasn't opened your bid request yet — hover it for Not viewed yet. From the bid request's header, use Remind All Bidders (also available on the Analyze Bids screen) to nudge anyone who hasn't responded.


Step 2: Open a response for the full detail

Click any row to open that response. You'll see its Status, the date it was submitted, and the Bid Amount tagged Lump Sum or Itemized, who it's From, their Scope of Work and Scope Breakdown, and any Attachments. An Internal Notes field — marked “Only your team can see this — never shared with the subcontractor” — is a good place to track bidder engagement, like “left voicemail 7/20, waiting on revised quote.”

If a sub submitted a lump sum with no line-item breakdown, click Generate Breakdown to have the assistant estimate one from the scope.

Click AI Analyze at the top of the response to have the assistant review that one bid against the scope you requested. It opens a panel on the left with a plain-language summary, a Confidence rating, Coverage for each scope item you asked for (items the bid doesn't address show as Not specified), Risk Flags, and Negotiation Points — and you can ask it follow-up questions about the bid. Use Hide Assistant to close the panel.

The Options menu on a response offers Preview, Reject, and Delete, and Award sits next to it.


Step 3: Add a bid you received outside KonstructIQ

Not every subcontractor uses the portal. You can log a bid that arrived by email, PDF, or phone right from the Responses tab, which has a Drag a Bid here area at the top.

  1. To upload a bid document, drag it onto Drag a Bid here or click Upload Bid. KonstructIQ reads the subcontractor, amount, and line items for you. Limits: PDF, PNG, or JPG, up to 25 MB.

  2. Or click Enter Manually to type it in yourself: pick the Subcontractor/Vendor (required), choose Bid Type (Lump Sum or Itemized), fill in Categories with a description and amount per line, and optionally add a Timeline, Scope of Work, Exclusions, Notes, and Internal Notes. A bid needs at least one line with an amount.

  3. Click Save Bid. It appears on the Responses tab alongside portal submissions, ready to review and award like any other.


Step 4: Compare bids side by side

Once at least 2 bids are submitted (up to 5), click Analyze Bids. The assistant compares Total Price, Scope Inclusions by category, Timeline, a Confidence rating, a Scope Summary, and Exclusions for every bid, side by side.

The panel on the left names a Recommended bid with its Key Drivers, and calls out Risk Flags — for example, when a sub's flat fee comes with no itemized scope, which raises the odds of a change order later. Ask the assistant follow-up questions about the bids directly from this screen.


Step 5: Award a bid — and reject the others

Click Award on a bid's response page (or from Analyze Bids). The confirmation shows the amount and category, and tells you the subcontractor will be notified by email and that other submitted bids move to Rejected.

Choose Award & apply to estimate to have the assistant ask a couple of questions and then produce the updated estimate for your review (see Step 6), or Award only to award and notify the sub now and decide on the estimate later — you can apply it any time from the bid's details page.

The Notify other subs that their bid wasn't selected checkbox is off by default. Check it if you want the other bidders to receive an email — the confirmation tells you how many will be sent. Exporting the bid as a PDF stays available either way.

Rejecting a bid without awarding. To decline a bid on its own, open it, click Options, and choose Reject. Awarding one bid on a request also moves the other submitted bids to Rejected.


Step 6: Apply an awarded bid to your estimate

If you chose Award only, or want to review before applying, open the awarded bid and click Apply to Estimate. The assistant reads the bid and your existing estimate in four steps — reading the bid, matching it against your estimate, resolving exclusions, and building a preview — then asks how to handle any overlap.

A lump sum bid lands as a single line and is never split across your existing items, so if the category already has items, the assistant asks whether to Remove covered items (replacing the old lines with the lump sum) or Keep existing items (adding the lump sum alongside them). Review the proposed changes — additions, deletions, and their dollar amounts — then click Apply.

Applying always saves a version of the estimate first, labeled Before BID-# — [Subcontractor]. Find it under the estimate's Options → View All Versions if you need to see or restore what the estimate looked like before the bid was applied.


Editing or closing a bid request

Once a bid request is sent, its Options menu offers Preview, Edit, Duplicate, and Close Bid Request.

Clicking Edit moves the bid request back to Draft — subcontractors won't see your changes until you send it again, and any new responses are paused while it's in draft. Existing responses already submitted aren't lost.

⚠️ Important: Close Bid Request stops it from accepting new bids and cannot be undone — once closed, a bid request cannot be reopened. Use it once you've awarded (or decided not to award) and want to shut the door on further responses.

Duplicate creates a new bid request with the same categories, scope items, and settings — useful for sending a near-identical request to a different set of subs, or re-bidding a scope that changed.


Troubleshooting & FAQs

  • How do I reject a bid I don't want? Open the bid, click Options, then Reject. Awarding a different bid also moves the other submitted bids to Rejected.

  • Will the other bidders be told they weren't selected? Only if you check Notify other subs that their bid wasn't selected in the Award confirmation. It's off by default.

  • Can I edit a bid request after I've sent it? Yes, from Options → Edit — but it moves the whole request back to Draft and pauses new responses until you send it again.

  • Can I reopen a bid request after closing it? No. Closing is permanent — the bid request can no longer accept new bids.

  • I awarded a bid without applying it to the estimate — can I still apply it later? Yes. Open the awarded response and click Apply to Estimate at any time.

  • Does applying a bid overwrite my estimate for good? No — applying always saves a version of the estimate first, so you can find the pre-bid version under Options → View All Versions.

  • Can I review a bid if only one subcontractor has responded? Yes — open the response and click AI Analyze to check it against your requested scope. Comparing bids side by side with Analyze Bids needs at least 2 submitted bids (up to 5).

  • A subcontractor emailed me a PDF instead of using the portal — do I have to re-key it? No — on the Responses tab, drag it onto Drag a Bid here or click Upload Bid, and KonstructIQ reads the subcontractor, amount, and line items for you.


Quick Reference

Path: bid request → Responses tab to track bids → Upload Bid or Enter Manually for one received outside KonstructIQ → open a response and AI Analyze to review it, or Analyze Bids to compare → Award (or Options → Reject) → Apply to Estimate → Options → Close Bid Request when done.

Limits: Analyze Bids needs 2–5 submitted bids; uploaded bid documents up to 25 MB (PDF, PNG, or JPG).

Don't skip: reading the award confirmation before confirming — awarding one bid moves every other submitted bid on that request to Rejected, and closing a bid request afterward cannot be undone.